Featured image: A large, weathered, hemispherical structure dominates the scene. AI-generated image; not a photograph of the reported event.
Ulster University has scrapped plans for a multimillion-pound indoor sports dome in Londonderry. Source: bbc.co.uk.
The university spent about £800,000 before cancelling the project.
Project Overview
The dome was first announced in 2024.
It was meant to host rugby, football, and Gaelic games.
It would also support community and musical events.
Ulster University called it a ‘first-of-its-scale facility’ for Northern Ireland.
Costs and Spending
Project-related activities cost £700,000.
Management and governance added £100,000.
Total spending reached £800,000.
Why the Project Was Cancelled
By August, the university said the project was no longer financially viable.
It pointed to a lack of sustainable funding for higher education in Northern Ireland.
Political Concerns
SDLP member Sinéad McLaughlin said the announcement had been made with ‘much fanfare’.
She called the dome ‘unaffordable’.
She questioned why so much money was spent before it was deemed unviable.
She said it was unfortunate it took so long to reach that conclusion.
Funding and Partnerships
The PeacePlus programme was to provide €10.86m (£9.16m).
PeacePlus is jointly supported by the European Union, UK government, Irish government, and Stormont.
However, the Special EU Programmes Body (SEUPB) confirmed no funding had been paid.
SEUPB says it is reviewing reallocation options.
It cannot guarantee any funding will go to the north-west.
University’s Commitment
Ulster University said it would contribute £8.3m to the dome.
The university said the facility would serve both sports and community needs.
As a commercial project, the dome would have cost over £1m annually to operate.
University leaders said it could not afford ongoing maintenance.